Direct answer
Use this worksheet after multiple contractors have priced the same base scope. Its job is to normalize differences in scope coverage, assumptions, quantities, allowances, exclusions, schedule, permits, payment structure, and closeout so the investor can see what each total actually represents.
This is not a contractor-rating tool. It is a proposal-comparability tool.
A. Bid round identity
Property: _________________________________________________
Scope version issued: _____________________________________
Bid due date: _____________________________________________
Prepared by: _____________________________________________
Contractors compared:
- Contractor A: ______________________________________________
- Contractor B: ______________________________________________
- Contractor C: ______________________________________________
- Contractor D: ______________________________________________
B. First-pass completeness check
| Required return item | A | B | C | D |
|---|---|---|---|---|
| Base total stated | ||||
| Allowances identified | ||||
| Alternates separated | ||||
| Assumptions identified | ||||
| Exclusions identified | ||||
| Permit responsibility stated | ||||
| Inspection responsibility stated | ||||
| Schedule / duration stated | ||||
| Payment structure stated | ||||
| Warranty terms stated | ||||
| Clarifications identified |
If one proposal leaves major fields blank, do not treat blank as “included.”
C. Base-scope totals
| Contractor | Submitted base total | Known adjustments needed for comparability | Leveled comparison total |
|---|---|---|---|
| A | |||
| B | |||
| C | |||
| D |
The leveled total is not a new contractor quote. It is an internal comparison view that makes known scope differences visible.
D. Scope-coverage matrix
Create one row for each meaningful work package.
| Scope item | A | B | C | D | Clarification needed? |
|---|---|---|---|---|---|
| Demolition | |||||
| Debris removal | |||||
| Drywall / patching | |||||
| Painting | |||||
| Flooring | |||||
| Cabinets | |||||
| Countertops | |||||
| Plumbing | |||||
| Electrical | |||||
| HVAC | |||||
| Roofing | |||||
| Exterior | |||||
| Cleaning | |||||
| Closeout |
Suggested status values:
- included;
- excluded;
- allowance;
- alternate;
- unclear;
- not applicable.
E. Quantity comparison
A price can look lower simply because a contractor assumed less quantity.
| Item | Owner / scope quantity | A | B | C | D | Difference matters? |
|---|---|---|---|---|---|---|
| Flooring SF | ||||||
| Paint SF / rooms | ||||||
| Cabinets LF / count | ||||||
| Doors | ||||||
| Fixtures | ||||||
| Other |
Do not “level” a quantity difference until you know whether it is an error, a different measurement method, or a real scope interpretation difference.
F. Allowance comparison
| Allowance category | Scope expectation | A amount / coverage | B amount / coverage | C amount / coverage | D amount / coverage |
|---|---|---|---|---|---|
| Flooring material | |||||
| Cabinets | |||||
| Fixtures | |||||
| Appliances | |||||
| Tile | |||||
| Other |
An allowance is only comparable when the coverage definition is comparable.
G. Assumptions register
| Topic | A assumption | B assumption | C assumption | D assumption | Owner decision required? |
|---|---|---|---|---|---|
| Hidden damage | |||||
| Existing utilities | |||||
| Owner-furnished items | |||||
| Permit fees | |||||
| Site access | |||||
| Existing substrate condition | |||||
| Other |
H. Exclusion comparison
| Exclusion | A | B | C | D | Must be added to get same outcome? |
|---|---|---|---|---|---|
| Permit fees | |||||
| Disposal | |||||
| Final clean | |||||
| Patching after trade work | |||||
| Painting after repairs | |||||
| Hidden damage | |||||
| Testing / startup | |||||
| Other |
I. Schedule and sequencing
| Question | A | B | C | D |
|---|---|---|---|---|
| Earliest start | ||||
| Expected duration | ||||
| Material lead-time concern | ||||
| Occupancy assumption | ||||
| Dependencies / owner decisions | ||||
| Crew continuity / sequencing notes |
A lower price can be operationally worse if it creates a schedule that misses the investor's actual property objective.
J. Permit, inspection, and regulated-work responsibility
| Topic | A | B | C | D |
|---|---|---|---|---|
| Permit required? contractor position | ||||
| Who applies? | ||||
| Fees included? | ||||
| Inspection coordination included? | ||||
| Licensed trade identified? | ||||
| Closeout documentation included? |
Do not use a bid worksheet to decide legal requirements. Use it to expose who is assuming responsibility and what needs jurisdictional verification.
K. Payment structure
| Payment event | A | B | C | D |
|---|---|---|---|---|
| Deposit | ||||
| Milestone 1 | ||||
| Milestone 2 | ||||
| Milestone 3 | ||||
| Final | ||||
| Retainage / holdback if applicable |
Then ask:
- Is payment tied to observable progress?
- Does the structure front-load too much money relative to verified work?
- Are material purchases identifiable?
- Is final payment connected to closeout obligations?
L. Change-management readiness
| Question | A | B | C | D |
|---|---|---|---|---|
| Written change-order process? | ||||
| Evidence required for hidden conditions? | ||||
| Price and schedule effect documented? | ||||
| Owner authorization required before extra work? |
M. Closeout comparison
| Closeout item | A | B | C | D |
|---|---|---|---|---|
| Punch correction | ||||
| Final condition photos | ||||
| Permit / inspection documentation | ||||
| Warranty docs | ||||
| Equipment info | ||||
| Final clean | ||||
| Access handoff |
N. Clarification questions before award
| Contractor | Question | Why it matters | Response | Scope / price changed? |
|---|---|---|---|---|
Keep clarifications in the project record so the final award does not depend on forgotten phone calls.
O. Final comparison summary
For each contractor, record:
Contractor A
Strengths of proposal: ____________________________________
Material gaps / risks: ____________________________________
Unresolved clarifications: _________________________________
Leveled scope confidence: high / medium / low
Repeat for each bidder.
Final decision test
Before award, can the investor answer:
- ☐ Which proposal most completely covers the intended outcome?
- ☐ Which differences are real price differences versus scope differences?
- ☐ Which allowances remain variable?
- ☐ Which exclusions could become later cost?
- ☐ Which assumptions could trigger changes?
- ☐ Which schedule best matches the property objective?
- ☐ Which payment structure aligns with observable progress?
- ☐ Which permit / inspection responsibilities are clear?
- ☐ Which closeout obligations are explicit?
If the answer is no, the proposals are not fully leveled yet.
Relationship to the bid-comparison guide
Use How to Compare Contractor Bids on an Investment Property Rehab for the reasoning and examples.
Use this worksheet to perform the actual leveling exercise.